Showing reosurce and work in same field
Hi
How can I display for each task in a 'gantt' view the resource and work? The default resource field has the format: {resource name}{[% allocated]}, ... and I would like: {resource name}{work(d)},{resource name}{work(d)}, {resource name}{work(d)}, ... This is much more useful I know I can see this information in the split view - task details form - but I will find this view very useful. Done some searches and can not find this answer so hope someone can help me? |
#2
|
|||
|
|||
I'm afraid this isn't possible. The Work field in a task view shows total work on the task - not broken down by each resource assigned. The Task Usage view is the best view to show each task and the assignment of each resource to the task.
|
#3
|
|||
|
|||
what about a macro?
|
#4
|
|||
|
|||
It may be possible to loop through each task and write the resource names and work into spare text fields, concatenate the fields, and then show in the Gantt chart view - but I'm afraid I'm not the person to give you details.
You may download the Project 2010 SDK from: http://www.microsoft.com/en-us/downl....aspx?id=15511 |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Data not showing from Access linked work sheet | shabbaranks | Excel | 0 | 01-08-2014 02:52 AM |
Yes/No field does not work in mailmerge | Abacus1234 | Mail Merge | 10 | 10-14-2013 06:37 AM |
Field not showing in Pivot Table Field List | kmcovington | Excel | 0 | 10-26-2012 10:14 AM |
Making the IF field work (not Mail Merge) | Caroline | Mail Merge | 5 | 04-11-2011 04:17 PM |
TOC Level 3 Field Not Showing Up (Word 2007) | freitag | Word | 1 | 01-26-2010 08:47 PM |