JonHarding JonHarding is offline Showing reosurce and work in same field Windows 7 64bit Showing reosurce and work in same field Office 2010 64bit
Novice
Showing reosurce and work in same field
 
Join Date: Aug 2014
Posts: 2
JonHarding is on a distinguished road
Default Showing reosurce and work in same field

Hi
How can I display for each task in a 'gantt' view the resource and work?


The default resource field has the format: {resource name}{[% allocated]}, ...
and I would like: {resource name}{work(d)},{resource name}{work(d)}, {resource name}{work(d)}, ...
This is much more useful
I know I can see this information in the split view - task details form - but I will find this view very useful.
Done some searches and can not find this answer so hope someone can help me?
Reply With Quote
  #2  
Old 08-15-2014, 06:39 AM
JulieS JulieS is offline Showing reosurce and work in same field Windows 7 64bit Showing reosurce and work in same field Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid this isn't possible. The Work field in a task view shows total work on the task - not broken down by each resource assigned. The Task Usage view is the best view to show each task and the assignment of each resource to the task.
Reply With Quote
  #3  
Old 08-16-2014, 10:02 PM
JonHarding JonHarding is offline Showing reosurce and work in same field Windows 7 64bit Showing reosurce and work in same field Office 2010 64bit
Novice
Showing reosurce and work in same field
 
Join Date: Aug 2014
Posts: 2
JonHarding is on a distinguished road
Default

what about a macro?
Reply With Quote
  #4  
Old 08-17-2014, 12:41 PM
JulieS JulieS is offline Showing reosurce and work in same field Windows 7 64bit Showing reosurce and work in same field Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It may be possible to loop through each task and write the resource names and work into spare text fields, concatenate the fields, and then show in the Gantt chart view - but I'm afraid I'm not the person to give you details.

You may download the Project 2010 SDK from:
http://www.microsoft.com/en-us/downl....aspx?id=15511
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Data not showing from Access linked work sheet shabbaranks Excel 0 01-08-2014 02:52 AM
Showing reosurce and work in same field Yes/No field does not work in mailmerge Abacus1234 Mail Merge 10 10-14-2013 06:37 AM
Field not showing in Pivot Table Field List kmcovington Excel 0 10-26-2012 10:14 AM
Showing reosurce and work in same field Making the IF field work (not Mail Merge) Caroline Mail Merge 5 04-11-2011 04:17 PM
TOC Level 3 Field Not Showing Up (Word 2007) freitag Word 1 01-26-2010 08:47 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft