#1
|
|||
|
|||
|
I have added a column that indicates red,yellow,or green for each individual task (see attachment), but I can't figure out how to combine and roll them up to the summary level. Can this be done?
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
Heading level numbering in 2010 - wrong after second header level 1
|
taran | Word | 3 | 07-08-2013 01:12 PM |
Custom field formula not working at summary task level
|
abw1987 | Project | 3 | 10-05-2011 07:17 AM |
Find summary level
|
AndreT | Project | 2 | 08-05-2011 09:56 PM |
| Text Highlighting in Yellow ??? | mark4man | Publisher | 0 | 12-15-2005 06:46 PM |