Milestones Filter to show Milestones within 2 months
I see a filter to show which milestones are due this month ("End of the month is:"?) but not modify that so that it shows milestones due within 2 months.
Greatly appreciate your help |
#2
|
|||
|
|||
Have you tried using the Autofilters on the Finish field? Add the Milestone Field to the table - filter for milestones = Yes. Then click the AutoFilter drop-down on the finish field, and select which months you wish to see.
|
#3
|
|||
|
|||
thanks for the reply, but applies to the gantt chart and not the report, right?
|
#4
|
|||
|
|||
What report are you using? What release of Project?
|
#5
|
|||
|
|||
Project 13 Standard, a modified version of project overview
|
#6
|
|||
|
|||
The usual Project Overview report shows all milestones in the Milestones table that are not complete. Are you referring to that table?
You can create a custom filter to show milestones that are 60 days to today. You'll first need to calculate the value for X days from the current date. Add a date field to the Gantt chart view. For this example, I used the [Date1] field. Customize the field with the following formula: ProjDateAdd([Current date], 60 * [Minutes per Day]) That will show you the date 60 days from the current date - so if today's date is August 13, I am seeing Nov 4. Adjust the increment (60) as needed to get the values you seek. Then create a custom filter - look at the attachment for the filter definition. In the Project Overview report - in the Milestones table - select the filter you created. |
#7
|
|||
|
|||
AWESOME!! thanks so much it worked.
|
#8
|
|||
|
|||
You're welcome and thanks for the feedback.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
events show some Calendar months, not others | stoddj | Outlook | 0 | 03-28-2013 07:18 AM |
Milestones: Display of - turning off the display of the date | Pmacdaddy | Project | 3 | 01-18-2013 05:42 PM |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |
Links to several milestones on same line of a Gantt chart | viv_2_k | Project | 3 | 08-03-2011 04:40 AM |
Link activities and milestones between projects (2003) | jowian | Project | 0 | 11-25-2010 09:10 AM |