#2
|
|||
|
|||
|
You may assign material resources at a specific cost per day. Add a hammock task to the project:
http://support.microsoft.com/kb/141733/en-us Create a material resource with a cost (standard rate) of $5000. Split your screen to show the Gantt chart in the upper pane and the task form in the lower pane. Select the material resource form Resource Name list and in the units field, enter 1/d to assign the $5000 resource at one per day. |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Need totoal cost despite project being in progress
|
Sognamed | Project | 1 | 07-23-2013 06:06 AM |
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
|
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
How to use fixed duration, fixed work and have resources/units leveled automatically?
|
Joeb | Project | 3 | 06-25-2012 04:18 PM |
| free slack changes when i paste from fixed cost to cost1 column | ketanco | Project | 5 | 02-03-2012 06:17 AM |
| Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |