joday48 joday48 is offline Multiple resources on one task Windows 7 64bit Multiple resources on one task Office 2010 32bit
Novice
Multiple resources on one task
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Multiple resources on one task

Hi all

I'm a little rusty. I'm working in 2010.

I have been given the durations (in days) that tasks will take. I have multiple resources, all of whom will be working on the same tasks, all assigned units will differ, example, resource A will spend 60%, B will spend 20% and C will spend 20%.

Apparently each resource with have a different number of effective hours per day.

How should I handle this in the schedule?



thanks

JD
Reply With Quote
  #2  
Old 07-31-2014, 09:29 AM
joday48 joday48 is offline Multiple resources on one task Windows 7 64bit Multiple resources on one task Office 2010 32bit
Novice
Multiple resources on one task
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Hi

Can anyone tell me if i can have multiple resources with different resource calendars assigned to the same tasks?

Thanks

Jo
Reply With Quote
  #3  
Old 08-01-2014, 08:56 AM
JulieS JulieS is offline Multiple resources on one task Windows 7 64bit Multiple resources on one task Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, of course. When you create resources, each has his/her own calendar. If Bob only works 6 hours per day - then change his calendar. However, if you want to say Bob can only produce 6 hours per day out of 8 hours - then don't change his calendar, set his max units at 75%. Then, when you assign Bob to the task, he will be assigned at 75% - the work for him will be calculated at 75% of duration. Or, you can enter his work and Project will calculate duration.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Multiple resources on one task Assign different resources with different colors to the same task Shir Project 9 05-05-2017 12:29 PM
Multiple resources on one task Allocating multiple resources to a task and splitting the hours pptdgc Project 1 07-22-2014 03:45 AM
Multiple resources on one task Task types with no Resources assigned mtaylor Project 1 05-24-2014 12:37 PM
Multiple resources on one task excel cannot complete this task with available resources - vlookup Taisho Excel 4 01-27-2012 03:09 AM
Multiple resources on one task How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:31 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft