Resource not getting enough hours allocated to them, therefore extending duration
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Resource not getting enough hours allocated to them, therefore extending duration

Hi

I have a base calendar of 8 hours per day.

Example:

I have Bob who has a resource calendar of 6 hours per day.
Joe has a resource calendar of 4 hours per day.

I assign them both to a 40 hour task as follows:



Bob at 80%, and Joe at 20%.

Why is the duration calculating 7.38 days?

Additionally when I go into the resource usage view, it shows the following that joe is only being allocated 0.8 work per day. This is extending the duration. Further more the dates are 31/07/14 - 13/08/14. This is not 7.38 days??!!

Please help!

Thanks

jo
Reply With Quote
  #2  
Old 08-01-2014, 08:54 AM
JulieS JulieS is offline Resource not getting enough hours allocated to them, therefore extending duration Windows 7 64bit Resource not getting enough hours allocated to them, therefore extending duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have assigned Joe at 20% of 4 hours per day (his calendar) which is .8 hours per day. You have assigned Bob at 80% of 6 hours per day (his calendar) which is 4.8 hours per day. If you want Bob to work 6 hours per day and Joe to work 4 hours per day, assign them at 100%.

I get 6.5 days calculated with a task start of July 31 at 8:00 am and a finish of August 13 at 12:00 pm. Bob is working 32 hours (80% of 40) and finishes at 12:00 pm on August 8 - and Joe is work 8 hours (20% of 40) and finishes on August 13 at 12:00 pm.

In File, Options what is your definition of "hours per day"".
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource not getting enough hours allocated to them, therefore extending duration Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM
Resource not getting enough hours allocated to them, therefore extending duration Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Resource not getting enough hours allocated to them, therefore extending duration Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Resource not getting enough hours allocated to them, therefore extending duration Over-allocated resource - resource holiday scott.hannaford Project 1 10-21-2013 05:32 AM
Resource not getting enough hours allocated to them, therefore extending duration Over allocated with only 1300 hours in a year?!!! msproject2010 Project 1 08-01-2011 04:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:29 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft