What is your work estimate for each package? If it's more than 10 hours of work per work package, you have a problem of lack of resources. You can certainly set up each of the 8 tasks as fixed duration (1 week) and assign a resource specify the work estimate. Project will spread the work out evenly over the 1 week duration. Assign 4 tasks to one resource and 4 to another. |
|