Guloluseus Guloluseus is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2010 32bit
Competent Performer
Changing units in resource work visual report
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default Changing units in resource work visual report

I need to produce resource visual reports in Project 2013, which is simple enough, however the vertical scale is always in man hours, whereas I need it in man days.


Can I set the report up to give me days? Currently I set the hours axis to hours/wk (usually default), then print as a pdf and edit t give me a day count. This takes to long and every time there is a change, I need to repeat the whole process.

thanks
Reply With Quote
  #2  
Old 07-22-2014, 03:46 AM
JulieS JulieS is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't have 2013 handy to check so I haven't tested - but does changing the work to "days" in File > Options, schedule work?
Reply With Quote
  #3  
Old 07-22-2014, 08:22 AM
Guloluseus Guloluseus is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2010 32bit
Competent Performer
Changing units in resource work visual report
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Dang it, meant 2010, NOT 2013. I have no idea at all how I mistyped that one... sorry!
Reply With Quote
  #4  
Old 07-23-2014, 01:13 PM
JulieS JulieS is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Not to worry. I have tested changing the setting and it does not having any effect on the Visual Report. The report shows everything in hours.
Reply With Quote
  #5  
Old 07-25-2014, 02:13 AM
Guloluseus Guloluseus is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2010 32bit
Competent Performer
Changing units in resource work visual report
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Yeah, its a bit annoying that it wont change over.
Can mark this as a solved as we have resorted to a workaround- the client has been given resource graphs for each labour group, which DO show labour in days. Given that this covers the contract requirements, fairly confident that this will work out.

the original programme was written in Primavera P6 (which I am learnig to loathe day by day) and after trying to produce reports in that I resorted to converting to Project and extracting info from there. At least Project will let you do that easily
Reply With Quote
  #6  
Old 07-25-2014, 10:39 AM
JulieS JulieS is offline Changing units in resource work visual report Windows 7 64bit Changing units in resource work visual report Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Glad you were able to get it sorted out and thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing units in resource work visual report Problem creating visual report shird Project 2 03-18-2019 03:44 AM
Changing units in resource work visual report Sub-Project and resource report codeghi Project 16 04-26-2014 08:27 AM
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Changing units in resource work visual report Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:33 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft