PeteS PeteS is offline Resource Assignment Summary Line Not Adding Up Correctly Windows 7 32bit Resource Assignment Summary Line Not Adding Up Correctly Office 2010 32bit
Novice
Resource Assignment Summary Line Not Adding Up Correctly
 
Join Date: Jul 2014
Location: Perth, AUS
Posts: 2
PeteS is on a distinguished road
Default Resource Assignment Summary Line Not Adding Up Correctly

Hi everyone!

I have trawled through numerous sources but am yet to find a resolution to the following issue, I hope someone can help! :-)

I'm currently using MS Project 2010 (SP2) along with PWA/Project Server 2010 and I'm having some issue with the assignment summary line for in the resource usage view not adding up hours correctly.



I have a resource that is working on multiple projects that are stored in project server.

When I first open up server I ensure the "Load assignments" tick box is checked.

I open up one of the project schedules and navigate to the resource usage view. It's showing some confusing figures at the summary line that sometimes doesn't add up the hours under the "Other Projects and Commitments" section.

I have reviewed the tasks in all the project schedules that the resource has been assigned work and they are all set to "auto schedule" and are a combination of manual and flat based work contoured assignments.

When I have all schedules from project server open (checked out and not read only) the summary line that adds up resource work hours changes to the correct figure.

Is this a bug in MS project or is there a setting that I am missing?

Happy to send a couple of example screen shots to anyone who is willing to help me.

Thanks in advance!

Pete
Reply With Quote
  #2  
Old 07-16-2014, 06:37 AM
JulieS JulieS is offline Resource Assignment Summary Line Not Adding Up Correctly Windows 7 64bit Resource Assignment Summary Line Not Adding Up Correctly Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Pete,
Not many server folks hang out here. I suggest posting to the Microsoft Project Server forum on TechNet:

http://social.technet.microsoft.com/...ver2010general
Reply With Quote
  #3  
Old 07-18-2014, 06:24 AM
JulieS JulieS is offline Resource Assignment Summary Line Not Adding Up Correctly Windows 7 64bit Resource Assignment Summary Line Not Adding Up Correctly Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Posted to:
http://answers.microsoft.com/en-us/o...3-8af3f493c9ce
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Resource Assignment Summary Line Not Adding Up Correctly Costs are not adding to the summary task in cost1 column ketanco Project 1 06-14-2012 03:23 PM
Resource Assignment Summary Line Not Adding Up Correctly Adding a goal line to a chart uhlersa Excel 1 01-16-2012 08:18 PM
adding a comma in end of each line in word juanb007 Word 0 07-23-2010 01:28 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft