Copy and Paste of a Task...Including all of the Task's 'children'...to a new task
How do I copy and task...including all of its children...and paste as a new task...within Project 2013?
(you would think that this would be a simple procedure..but every time I attempt to 'copy and paste' an existing task...in order to create an exact replication of it...the parent-child relationships are not maintained!) |
#2
|
|||
|
|||
Collapse the detail tasks by clicking the black triangle. Select the Summary task by clicking on the Task ID (row number).
Copy and paste. Please also ensure you have SP-1 installed to Project 2013. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
copy paste task names and relations only | ketanco | Project | 5 | 06-18-2014 12:56 PM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Can no longer copy and paste an email file into a task | kc300c | Outlook | 0 | 07-16-2010 04:34 PM |