#1
|
|||
|
|||
![]()
in my construction schedule i am showing only installation items but for two important long lead time equipment, i like to show fabrication durations too and link submittals and installation to those as they are important and long time.
but my schedule is only a construction installation schedule for the field is there a way to show and link those items but still exclude them from the % calculations? for example because they are long lead time, if they are not yet started, it affects the % complete of my project negatively although in the field there is a lot of progress by the way everything is calculated per durations in my schedule, as the default option. (physical % complete show 0 for everything even completed ones for example. i did not assign any resources. i go by durations) |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ms3433 | Outlook | 1 | 09-05-2013 11:03 AM |
outlook renaming all categories to schedule | aircm | Outlook | 0 | 05-09-2012 07:45 PM |
Need to Create a Resource Driven Schedule | gamer83 | Project | 2 | 05-24-2011 03:56 AM |
Powerpoint project schedule | L J Keane | Project | 0 | 09-14-2010 01:24 AM |
Outlook 2007 Saved sent items list only holds the last ten items | david.peake | Outlook | 0 | 06-01-2010 07:27 PM |