ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default critical activity with floating end date

my activity B has two successors. G with SS relation, and D with FS relation

all of them are critical

so B and G are critical because of their SS relation

but finish date of B is not pushing D, there is a 1 day gap. D is pushed by something else

I checked all float dates for B and everything shows 0. I understand that Total Float is 0, but all other floats also relate to start date of B then? so although B end date has 1 day of float it doesnt mean anything?
Reply With Quote
  #2  
Old 06-15-2014, 09:05 AM
JulieS JulieS is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What is the driving predecessor to Task D? Is D linked to another task as well?
Reply With Quote
  #3  
Old 06-16-2014, 06:42 AM
ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

let me write the relations and durations of these actvities only as the rest of activities are irrelevant.
Activity B : (Dur: 2 days) (Pred: irrelevant) (Succ: G(SS), D)
Activity D : (Dur: irrelevant) (Pred: B, G) (Succ: Irrelevant)
Activity G : (Dur: 3 days) (Pred: B(ss)) (Succ: D)

and all are critical in the schedule

So as you can see, B is making G critical by affecting its start date, and Both B and G are pushing D with FS. since D is 1 day longer than B, there is a 1 day float for finishing B. So although Start of B can not move, and the program says Total Float is 0 and I understand that, still we could make B 1 day longer, and the job would not delay. but all types of floats still show 0. so does it mean, all types of floats only depend on start dates?
Reply With Quote
  #4  
Old 06-16-2014, 11:06 AM
JulieS JulieS is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The reason task B is critical is due to the relationship (SS) with G. Float is determined by the forward pass (calculation of early start and early finish) and the backwards pass (late start and late finish). If there is no difference between a tasks Finish and Late Finish or Start and Late start, the task is critical.
Take a look at the Schedule table to see late start and late finish. The dates will match task B's start and finish.
Reply With Quote
  #5  
Old 06-16-2014, 11:39 AM
ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

yes B is critical because of SS relation to G. and yes, critical activity is determined as you say. and here is also B finsih and Late finish date is same. because program thinks B's duration of 2 days as a fixed unchangeable thing.

but as you can see there is a 1 day gap between B end date and D start date. in other words, lets say B starts, and while performing B, something happens and B slows down and finish by 1 day delay. it will still be ok, no delay to the project will occur, although B is critical. Because B is only critical because of its start date, and NOT its finish date. and where is this information reflected? I assume nowhere?
Reply With Quote
  #6  
Old 06-16-2014, 12:58 PM
JulieS JulieS is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The fact that the finish of B can be delayed by one day (currently) is not reflected anywhere directly in this release. G is the driving predecessor and you can see that in the task inspector for Task D. Task B is not listed in the inspector window as it is not currently driving D.
Reply With Quote
  #7  
Old 06-17-2014, 07:42 AM
ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

by saying in this release do you mean all MS project versions? but as far as scheduling terms is there a definition for this? although MS project doesn't cover it?
Reply With Quote
  #8  
Old 06-17-2014, 10:17 AM
JulieS JulieS is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

In Project 2013 you can view all successors or driven successors as well as all predecessors as well as driven predecessors.

I do not know if there is a scheduling term for this.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
critical activity with floating end date floating month prompt schroca Word 2 05-12-2014 06:32 PM
critical activity with floating end date activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical activity with floating end date change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
critical activity with floating end date Floating object help ic-uc Drawing and Graphics 2 12-15-2008 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:51 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft