ketanco ketanco is offline milestone with more than 0 day duration Windows 7 64bit milestone with more than 0 day duration Office 2010 64bit
Expert
milestone with more than 0 day duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default milestone with more than 0 day duration


in the milestone column i marked yes for an activity of 4 days duration (which happens to be a critical activity). and it became a milestone, still with 4 day duration but it is not shown as critical anymore , it is not in red at least. is it still critical? how does a milestone with a duration differ from a milestone of 0 duration? when we say milestone we understand by default 0 day correct?
Reply With Quote
  #2  
Old 06-16-2014, 02:56 AM
Guloluseus Guloluseus is offline milestone with more than 0 day duration Windows 7 64bit milestone with more than 0 day duration Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

A milestone by definition is a 0 duration activity- it is not an event in itself, but signifies that other tasks have been completed or that a point has been reached. Even the help within Project indicates this.

I cannot see how a 4 day activity should be marked as a milestone. If you need a milestone at this point, I would suggest inserting a new activity after the 4 day event (call it "xxx complete or whatever is significant), and link the 4 day activity to this, with the successors being transferred to the new milestone.

If you look under format (on the main tabs), choos format/ bar styles, you will see that a milestone is shown as a diamond- a 0 duration task.
A new item would establish the milestone, without affecting th eprogramme.
Reply With Quote
  #3  
Old 06-16-2014, 06:25 AM
ketanco ketanco is offline milestone with more than 0 day duration Windows 7 64bit milestone with more than 0 day duration Office 2010 64bit
Expert
milestone with more than 0 day duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

well the program marked it as a milestone and that is my question. how can a 4 day activity be a milestone? in addition to marking it as a milestone, the program also made it noncritical (as least it is not red in color anymore). so my question still stands... anyone?
Reply With Quote
  #4  
Old 06-16-2014, 11:00 AM
JulieS JulieS is offline milestone with more than 0 day duration Windows 7 64bit milestone with more than 0 day duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You may mark any non zero duration task as a milestone through Task Information, Advanced. I never do it as I follow the usual definition of milestones = zero duration.

The color of the task bar does not necessarily indicate that the task is not critical. Check the Total Slack for the task to see if it is critical.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
milestone with more than 0 day duration Is my Milestone working that way it's suppose to? Enuhseh207 Project 1 02-23-2014 09:24 AM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
milestone with more than 0 day duration calculating duration ketanco Project 5 12-15-2011 07:15 PM
milestone with more than 0 day duration Duration does not change caz46 Project 1 05-17-2011 07:51 AM
Project 2010 - Milestone Font Colour OTPM Project 1 05-11-2011 03:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:44 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft