ms project 2010 calculating logic
lets say, i assigned the logic of
1FS+2days to task number 3 as a predecessor. so it needs to start after 2 days of finish of task 1 corrrect? but i just started using ms project 2010 and it doesnt do that. it starts somewhere else, even before finish of task 1 for some reason. and there is no other predecessor to it. why can this happen? |
#2
|
|||
|
|||
ok it was due to settings of manual vs auto calculation. i saw that it does it for new tasks whic is the case from now. but for existing tasks i need to change from manual to auto one by one right?
|
#3
|
|||
|
|||
No. You can select multiple tasks and you the task mode setting on the Task Ribbon to change to auto scheduled.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project not calculating earned value correctly | mtbtomo | Project | 1 | 10-23-2013 06:49 AM |
What logic does P.P. use to move elements on theme change? | Malcom | PowerPoint | 2 | 05-24-2013 02:55 AM |
weird page numbering logic in word 2013 | dylansmith | Word | 5 | 02-20-2013 07:08 PM |
total slack of activities and schedule logic | ketanco | Project | 1 | 08-04-2012 05:58 AM |
summary task calculating from project start | ketanco | Project | 1 | 01-02-2012 02:34 PM |