ms project 2010 calculating logic
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default ms project 2010 calculating logic

lets say, i assigned the logic of


1FS+2days to task number 3 as a predecessor.
so it needs to start after 2 days of finish of task 1 corrrect?
but i just started using ms project 2010 and it doesnt do that. it starts somewhere else, even before finish of task 1 for some reason. and there is no other predecessor to it. why can this happen?
Reply With Quote
  #2  
Old 06-13-2014, 11:11 AM
ketanco ketanco is offline ms project 2010 calculating logic Windows 7 64bit ms project 2010 calculating logic Office 2010 64bit
Expert
ms project 2010 calculating logic
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

ok it was due to settings of manual vs auto calculation. i saw that it does it for new tasks whic is the case from now. but for existing tasks i need to change from manual to auto one by one right?
Reply With Quote
  #3  
Old 06-15-2014, 09:03 AM
JulieS JulieS is offline ms project 2010 calculating logic Windows 7 64bit ms project 2010 calculating logic Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No. You can select multiple tasks and you the task mode setting on the Task Ribbon to change to auto scheduled.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
ms project 2010 calculating logic MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
ms project 2010 calculating logic What logic does P.P. use to move elements on theme change? Malcom PowerPoint 2 05-24-2013 02:55 AM
weird page numbering logic in word 2013 dylansmith Word 5 02-20-2013 07:08 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
ms project 2010 calculating logic summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:01 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft