Old 06-13-2014, 11:33 AM
ravl13 ravl13 is offline How to make a task adjust its end date depending on another task? (Newbie) Windows XP How to make a task adjust its end date depending on another task? (Newbie) Office 2007
Advanced Beginner
How to make a task adjust its end date depending on another task? (Newbie)
 
Join Date: Nov 2012
Posts: 50
ravl13 is on a distinguished road
Default How to make a task adjust its end date depending on another task? (Newbie)

Hello,



I have a project where I want to keep track of the Project Manager's work dates, as well as the Project dates, as tasks. In the below screenshot, I know that the "Rework Coding" task (row 18) will be the last real task to be completed. How can I make the "Project Manager" Subtask (row 3) and the "Eforward" task (row 1) automatically adjust their end dates to match the end date of the Rework Coding task? So if I change the Finish date of the Rework Coding task, the Finish date of the Project Manager Subtask and Eforward task will change along with it?

http://imgur.com/faQVvTF
Reply With Quote
  #2  
Old 06-15-2014, 09:04 AM
JulieS JulieS is offline How to make a task adjust its end date depending on another task? (Newbie) Windows 7 64bit How to make a task adjust its end date depending on another task? (Newbie) Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Use a hammock task.

http://support.microsoft.com/kb/141733/en-us
Reply With Quote
  #3  
Old 07-27-2014, 09:50 AM
ravl13 ravl13 is offline How to make a task adjust its end date depending on another task? (Newbie) Windows XP How to make a task adjust its end date depending on another task? (Newbie) Office 2007
Advanced Beginner
How to make a task adjust its end date depending on another task? (Newbie)
 
Join Date: Nov 2012
Posts: 50
ravl13 is on a distinguished road
Default

That's what I needed, thanks
Reply With Quote
  #4  
Old 07-27-2014, 06:10 PM
JulieS JulieS is offline How to make a task adjust its end date depending on another task? (Newbie) Windows 7 64bit How to make a task adjust its end date depending on another task? (Newbie) Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to make a task adjust its end date depending on another task? (Newbie) Newbie q - Create a filter for report in ms project 2013 task due in 2 weeks bypm Project 7 07-10-2015 06:19 AM
How to make a task adjust its end date depending on another task? (Newbie) Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
How to make a task adjust its end date depending on another task? (Newbie) Manual Task End Date rfmnz Project 1 12-16-2013 08:02 AM
How to make a task adjust its end date depending on another task? (Newbie) Passed due task end date tcalderini Project 1 09-19-2013 04:56 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:58 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft