lets say, i assigned the logic of
1FS+2days to task number 3 as a predecessor.
so it needs to start after 2 days of finish of task 1 corrrect?
but i just started using ms project 2010 and it doesnt do that. it starts somewhere else, even before finish of task 1 for some reason. and there is no other predecessor to it. why can this happen?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
ms project 2010 calculating logic MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
ms project 2010 calculating logic What logic does P.P. use to move elements on theme change? Malcom PowerPoint 2 05-24-2013 02:55 AM
weird page numbering logic in word 2013 dylansmith Word 5 02-20-2013 07:08 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
ms project 2010 calculating logic summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:22 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft