#1
|
|||
|
|||
Master Project Weekly Summary Issue
Hi everyone,
I have a master project that combines several sub projects that contain identical sub tasks. When I review the master project by week, I only see the task names and not the parent task. As a result I end up with a series of 'tasks' that all have the same name making it impossible to figure out what the actual item refers to. Attached is a screen grab to hopefully clarify this. I guess the question is: "How do I display the parent task for a summary view?" Thank you |
#2
|
|||
|
|||
It appears that you are grouping by start date? If so, click the group drop-down and select the option "Maintain hierarchy in current group."
|
#3
|
|||
|
|||
Perfect! That did the trick.
Thanks |
#4
|
|||
|
|||
Great. Thank you for the feedback.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
Collapseable summary tabs are not seperatable project 2010 | cryoffalcon | Project | 5 | 08-11-2012 05:28 AM |
project summary | ketanco | Project | 1 | 01-02-2012 02:35 PM |
summary task calculating from project start | ketanco | Project | 1 | 01-02-2012 02:34 PM |
Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |