#1
|
|||
|
|||
Performing filtering to tasks that occur during the next three months
In project 2010, I want to see only the tasks that happening in the next 3 months. For example tasks that happening between 1/6/14 to 1/9/14: the task can start before 1/6/14 and end after 1/9/14. or - start after 1/6/14 and end before 1/9/14 etc. Please Your help, Thanks in advance |
#2
|
|||
|
|||
Hi
You can use the Date Range filter for this. Click on the View tab followed by clicking on the little arrow next to the Filter drowdown box and choose Date Range... Hope this helps. Tony |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to get simultaneous and sequential animations to occur together | seanspotatobusiness | PowerPoint | 1 | 03-06-2014 10:02 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
Excel 2011 not performing paste special correctly | mzimmers | Excel | 1 | 01-04-2011 06:17 AM |
Setting up recurring months to skip some months etc. | dwelch@ykfireprevention.c | Outlook | 0 | 11-30-2010 10:15 AM |
Filtering Tasks | timvb85 | Outlook | 0 | 11-15-2010 08:30 PM |