#1
|
|||
|
|||
Fixed Work Hours - newbie question
Hi all- I was looking for some suggestions as to how to build an internalized timeline for a project I'm working on. I have a main timeline for client and management viewing purposes, but as a PM, I obviously have to also manage what my team is doing each day in order to meet the deliverables on the main timeline.
My team, for the most part, works on 2 projects at a time. The project i am running, as well as another. So, I have to set up each resource as only being able to work 4hrs a day. I am fine with setting up the resources work schedule for 4hrs per day (8am-12pm), but I am curious if I should also be editing the Schedule under File>Options>Schedule, under "calendar options for this project"? It shows that you can change the default start time, hours per day, hours per week, & days per month. I have more questions in regards to utilizing resources, but it's Monday, and I'm trying to pick up where i left off on Friday with my 'testing' with Resources in Project . I'll post when I recall my other difficulties! Thank you! E |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all | Evgeny | Project | 3 | 01-03-2013 06:45 AM |
How to use fixed duration, fixed work and have resources/units leveled automatically? | Joeb | Project | 3 | 06-25-2012 04:18 PM |
Work Week: hours vary each day | rkc | Outlook | 1 | 08-31-2011 01:17 PM |
newbie question | DanSandbergUCONN | Word | 5 | 03-06-2011 04:27 PM |
Perhaps a newbie question I know but | as1947 | Excel | 0 | 02-05-2009 08:01 AM |