#1
|
|||
|
|||
Assigning resources not shortening task period
I have a project that has a duration of 2480 hrs with a start date set. Even though I have four resources at 100% the finish date is approximately 14 months out. It seems Project is only accounting for one person not four. How do I get it to see all four resources working the hours so that the finish date pulls in earlier. |
#2
|
|||
|
|||
In order for the addition of resources to shorten the task duration, the task needs to be effort driven. Show the task form in the lower pane. It will allow you to easily view status information (Task Type, Effort driven or not) as well as view the work assigned to each resource.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Fixing Work, % of actual work and Final Date in a task (while assigning resources) | Campelliann | Project | 1 | 01-09-2017 06:15 PM |
Assigning Resources and percent complete | jwindholz2725 | Project | 1 | 02-24-2014 10:56 AM |
Assigning Resources to Tasks | rickw262 | Project | 1 | 01-18-2013 04:46 AM |
Assigning calendars to resources automatically | david_23 | Project | 3 | 03-30-2012 07:43 AM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |