Old 05-26-2014, 09:10 PM
pm37064 pm37064 is offline Once you have a % complete does it always lock in the dates? Windows 7 32bit Once you have a % complete does it always lock in the dates? Office 2013
Novice
Once you have a % complete does it always lock in the dates?
 
Join Date: May 2014
Location: Hong Kong
Posts: 1
pm37064 is on a distinguished road
Default Once you have a % complete does it always lock in the dates?

I am using a project plan from an artifact folder set up by my work group. This project plan "master" is set as it should be for a brand new project. All durations are set up as though nothing is complete and % complete is at "0" also as it should be.



My problem is the project we are starting already has many of the tasks 100% complete so I prefer to set these tasks to "0" days duration and 100% complete to get an early estimate of how long the project will take. However once I set any % complete it locks the start and end date in place and I have to then go back, set the % complete to "0%" change the duration time and then go back again and change the % complete to 100%.

Is there a way to change a setting so I can change durations and % complete separately so it doesn't lock in start and end dates?
Reply With Quote
  #2  
Old 05-27-2014, 07:38 AM
JulieS JulieS is offline Once you have a % complete does it always lock in the dates? Windows 7 64bit Once you have a % complete does it always lock in the dates? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

When you add progress to a task, Project enters an Actual Start date. If you wish to control when a task started, show the Tracking Table and specify Actual Start and % complete.

If you want to set the tasks as milestones, first enter the zero duration then enter Actual Start and 100% complete.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Once you have a % complete does it always lock in the dates? Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
Any way to lock tab stops ctenanthe Word 1 01-31-2013 11:20 PM
Once you have a % complete does it always lock in the dates? complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
Num Lock ERROR judicial85 Excel 6 05-04-2012 10:43 AM
Once you have a % complete does it always lock in the dates? % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:15 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft