![]() |
#1
|
|||
|
|||
![]() Hi, I hope someone can help me figure this out. May sound dumb, but hey, no harm in asking. Since task types, resources and effort driven option all tie in together, does it matter if using Fixed Units or Fixed Duration for tasks don't have resources assigned and are not effort driven? FYI - Project tasks are currently as Fixed Units. Thanks |
#2
|
|||
|
|||
![]()
Task types and effort-driven have no effect unless there are resources assigned.
|
![]() |
Tags |
fixed duration, fixed units, task |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Excel cannot complete this task with available resources. Choose less data or close | YounesB3 | Excel | 1 | 11-16-2012 02:40 PM |
I am unsure I assigned a task out to a resource. | jsteczak | Project | 3 | 10-05-2012 04:41 AM |
![]() |
Taisho | Excel | 4 | 01-27-2012 03:09 AM |
![]() |
lukusm | Project | 1 | 01-16-2012 07:21 AM |
Task Form disappearing when assigned | zoids | Outlook | 0 | 03-27-2011 05:01 PM |