Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 05-14-2014, 09:46 AM
SaraJH SaraJH is offline Hammock task issue Windows 7 64bit Hammock task issue Office 2010 64bit
Novice
Hammock task issue
 
Join Date: May 2014
Posts: 2
SaraJH is on a distinguished road
Default Hammock task issue

Hi,

What a fantastic site! Hopefully you will be able to help me with a problem I have in MS Project.

I have a hammock task in my plan linked to the Project Start milestone and Project Complete milestone. The Hammock task is set to Fixed Work.

When I assign 90 days work to this task the start date moves away from project start (project duration is 225 days). I thought that the purpose of hammock tasks was that they didn't behave like this or am I doing something woring?

Many Thanks


Sara.
Reply With Quote
  #2  
Old 05-14-2014, 01:25 PM
JulieS JulieS is offline Hammock task issue Windows 7 64bit Hammock task issue Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Add the task to the schedule, and set it as fixed work. Assign the resource and specify the number of work hours. Then do the paste link to the Project start and Project Finish. However - are you sure it's fixed work? If the duration of the project increases, shouldn't the work increase as well?
Reply With Quote
  #3  
Old 05-15-2014, 01:40 AM
SaraJH SaraJH is offline Hammock task issue Windows 7 64bit Hammock task issue Office 2010 64bit
Novice
Hammock task issue
 
Join Date: May 2014
Posts: 2
SaraJH is on a distinguished road
Default

Thanks Julie,

I was doing things the wrong way around!

The plan is for a project estimated to start much later this year so at present I'm anticipating a start date change (which will then drive a change to the end date) but with the duration remaining the same.
Reply With Quote
  #4  
Old 05-15-2014, 05:52 AM
JulieS JulieS is offline Hammock task issue Windows 7 64bit Hammock task issue Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. Make sure you are changing the Project Start date through Project Information.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto scheduling issue - longest task first? Project_64 Project 3 01-25-2016 01:14 PM
Hammock task issue Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Hammock task issue Use VBA to create Hammock Tasks seanpears99 Project 1 03-08-2013 08:58 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
Outlook issue--task list Renee Arena Office 0 01-23-2006 11:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:24 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft