How obtain accurate total of hours estimated of all subtasks that are a certain type?
How obtain accurate total of hours estimated of all subtasks that are a certain type?
We have a project plan and of course there are many tasks with subtasks underneath each task Example: Task Estimated Work Hours Actual Work Hours Task type Overall Project Data entry screen 32 14 Define Requirements 8 5 Requirement Write Specification 8 6 Spec Perform Coding 8 3 Coding Conduct Testing 8 0 Testing +Reporting 40 24 Define Requirements 16 15 Requirement Write Specification 8 6 Spec Perform Coding 8 3 Coding Conduct Testing 8 0 Testing Question: When we perform a filter on the TASK TYPE column and select "Spec" WE STILL have the same total of hours (32,24 respectively) at the task level and even at a roll-up project level.. We want to determine how many hours total are "Spec" related for these 2 tasks. Any way to do this without exporting it to Excel or without adding up the columns manually that have the word "Spec" in that column? Thank you Peter |
#2
|
|||
|
|||
Filtering does not remove data - you'll need a custom group. I'm assuming you have some sort of custom field for the Coding, Requirement, Testing values. Create a custom group to group by the custom field. It will group by the field and summarize the work values. (assuming you have the field in the table.)
|
#3
|
|||
|
|||
Grouping, need help
When I did a group by Text1 which is the Phase Type field it did sum up the type but lost the task name. I would like the type summed up by each task. Not sure how to do this. Apologize for my newbie question. Here is what happened....
I put the file at www.peterbio.com/tempit So I am looking to show the total hours for the type "spec" by each task with the task name listed. I have a 700 line project plan. Thanks Peter |
#4
|
|||
|
|||
When you created the group, did you select the option "Maintain hierarchy"?
That will show task and summary names. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Using MS Project for Training subtasks | Robz | Project | 1 | 03-03-2014 05:13 AM |
How to obtain the inverse tan of a value in degree/minute second? | Jamal NUMAN | Excel | 3 | 07-27-2013 10:18 AM |
Subtasks | Mrnorth | Project | 3 | 06-11-2013 05:53 AM |
Baseline1 estimated finish - export to excel - data disconnect. - MSProject 2010 SP1 | stct | Project | 1 | 04-23-2013 05:11 AM |
Show selected summaries and subtasks | AndreT | Project | 0 | 01-14-2011 02:43 PM |