Total Slack and Activity with SS Successor only
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default Total Slack and Activity with SS Successor only

By definition Total slack is how much we can delay the START of an activity. But what type of slack do we have for delaying the FINISH of an activity?



I have an activity that has just one successor, and it is linked as

Activity 2 = Activity 1 SS + x days

My schedule says that Activity 1 has total slack of, say, 2 days.

But even if I increase the duration of my activity by more than 2 days, its total slack doesnt change.

So it means it is only affected by the start date of that activity. What type of slack do we have for delaying finish of it?
Reply With Quote
  #2  
Old 05-14-2014, 01:34 PM
JulieS JulieS is offline Total Slack and Activity with SS Successor only Windows 7 64bit Total Slack and Activity with SS Successor only Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure where you got that definition of Total Slack. Total slack is the difference between late start and start or late finish and finish. From help:

The Total Slack field contains the time a task's finish date can be delayed without delaying the project's finish date.

If a task's only successor is SS then delays to the end of the task have no effect unless the finish of the predecessor task goes past the successor. However, the task may very well have zero total slack because any change to its start will change the successor start.
Reply With Quote
  #3  
Old 05-14-2014, 01:53 PM
ketanco ketanco is offline Total Slack and Activity with SS Successor only Windows 7 64bit Total Slack and Activity with SS Successor only Office 2007
Expert
Total Slack and Activity with SS Successor only
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
I'm not sure where you got that definition of Total Slack. Total slack is the difference between late start and start or late finish and finish. From help:

The Total Slack field contains the time a task's finish date can be delayed without delaying the project's finish date.

If a task's only successor is SS then delays to the end of the task have no effect unless the finish of the predecessor task goes past the successor. However, the task may very well have zero total slack because any change to its start will change the successor start.
ok so if the only successor is SS, then the total slack definition is not true isnt it? so in other words, for a proper schedule to exist, we must always tie the finish of each activity to something
Reply With Quote
  #4  
Old 05-14-2014, 01:59 PM
JulieS JulieS is offline Total Slack and Activity with SS Successor only Windows 7 64bit Total Slack and Activity with SS Successor only Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No, I wouldn't say total slack definition is not true if you have SS links. I would say that start to start links mean that the finish of the task in question has no impact on the end date of the project, unless the finish extends past the latest date.

You need to review the logic in your project and determine what are the correct link types for each relationship. Tasks without successor or tasks with only a SS link imply that the finish of that task will not affect any other task in the project.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Total Slack and Activity with SS Successor only activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
Total Slack and Activity with SS Successor only seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM
Total Slack and Activity with SS Successor only total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
Total Slack not updating damianb Project 0 06-25-2010 11:48 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:13 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft