starting a task at half day
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default starting a task at half day

I have sevaral activities using 24 hour calendar. The first activity must start friday afternoon and starting that point it is a 24 hour calendar job (befor ethis it is normal calendar). Because the whole 24 calendar portion will last only 3 days, over a long weekend, it must start on friday afternoon and finish Tuesday morning. (from 8/29 afternoon to 9/2 early morning)

First of all is it possible to show that it starts 8/29 afternoon? and then the first tasks finish saturday afternoon and finish monday morning... then next set of tasks will take another 24 hours. so i must be able to divide the units to hours for that portion I guess, but the rest of the schedule before is in days units as usual. so is this possible?
Reply With Quote
  #2  
Old 05-12-2014, 10:46 AM
JulieS JulieS is offline starting a task at half day Windows 7 64bit starting a task at half day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You may turn on the display of time to show when tasks begin and end. For Project 2007, Tools > Options, General tab.
Reply With Quote
  #3  
Old 05-13-2014, 05:37 AM
ketanco ketanco is offline starting a task at half day Windows 7 64bit starting a task at half day Office 2007
Expert
starting a task at half day
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

on MS project 2007 I couldnt see this
Reply With Quote
  #4  
Old 05-13-2014, 07:16 AM
JulieS JulieS is offline starting a task at half day Windows 7 64bit starting a task at half day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Sorry, View tab.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
starting a task at half day Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
starting a task at half day Task not rolling up after single task was baselined Hwlr Project 1 06-05-2013 03:43 PM
one-half space? markbh Word 2 07-05-2012 10:08 PM
Half Page breaks Meltron3030 Word 2 02-22-2012 10:34 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:32 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft