ketanco ketanco is offline activities with 24 hour calendar - how to show proper duration Windows 7 64bit activities with 24 hour calendar - how to show proper duration Office 2007
Expert
activities with 24 hour calendar - how to show proper duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default activities with 24 hour calendar - how to show proper duration

I assigned the 24 hour calendar to some of the activities. before assigning, I had entered their duration when they had standard calendar. but now for example even if it says 2 day duration, it shows the start and finish the same day, because of 24 hour calendar so it doesnt make sense. how can I show durations of those activities properly? so when i say 2 days for that, I mean 2 days based on 24 hour calendar now. i also tried entering hours to work column but when i do that nothing change for duration
Reply With Quote
  #2  
Old 05-12-2014, 10:45 AM
JulieS JulieS is offline activities with 24 hour calendar - how to show proper duration Windows 7 64bit activities with 24 hour calendar - how to show proper duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can only define the definition of a "day" once per project file. My suggestion is to assign resources and specify their work. 24 hours of work on the standard calendar will take 3 working days from beginning to end. The same task assigned the 24 hours calendar will start and finish in a 24 hour period.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Differentiate certain activities from hypotetical activities in gantt chart Serena Project 1 02-24-2014 10:47 AM
events show some Calendar months, not others stoddj Outlook 0 03-28-2013 07:18 AM
activities with 24 hour calendar - how to show proper duration Meetings don't show in personal calendar Sneezy Outlook 1 12-12-2012 05:35 AM
activities with 24 hour calendar - how to show proper duration changing calendar vs duration ketanco Project 5 05-22-2012 01:04 PM
activities with 24 hour calendar - how to show proper duration Is it possible to show the Task due date in the calendar? Lin Outlook 1 07-26-2010 05:34 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft