#1
|
|||
|
|||
assign weekend 24 hr calendar to some tasks
Hello,
On my schedule, I am using the standard calendar for everything, but for only some of the activities I must use a calendar that will go through weekend and 24 hours. So first I entered the tasks using normal calendar, not doing anything special. Now the schedule knows that the amount of work for a 2 day tasks I say there is 16 hours correct? Only then, when I adjust the calendar to a 24 hour calendar, it will reduce the duration to 1 day? And I saw that there is a readily available 24 hour calendar, but I need a 24 hour AND weekend calendar together so I must create a new one and assign that one to these tasks right? So is my logic correct when I said I first enter them using normal calendar so project knows that normall it is a 2 day task? And how do I assign some of the tasks to the calendar - I open the advanced view of EACH of those activities one by one and assign my 7/24 calendar to them? |
#2
|
|||
|
|||
The 24-hours calendar in Project already includes weekends as working time. It is 24 hours per day 7 days per week 365 days per year.
A 16 hour task will still show as 2 days duration because although you have assigned the 24 hours calendar, the definition of "day" = 8 hours. The start and finish date/times will be correct. Add the Task Calendar field to a task view to quickly set calendars. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
work during weekend outside normal calendar | Intruder | Project | 13 | 02-27-2014 01:35 PM |
Assign resource groups to tasks | jjmclell | Project | 2 | 12-17-2012 04:28 AM |
Calculating Weekend Allowance | WinIDS | Excel | 6 | 09-02-2011 01:27 AM |
Change font size of tasks in pane under Calendar | ghumdinger | Outlook | 2 | 08-16-2011 06:29 PM |
Code to auto-forward weekend messages | Whang | Outlook | 0 | 06-16-2010 02:18 PM |