Hello,
On my schedule, I am using the standard calendar for everything, but for only some of the activities I must use a calendar that will go through weekend and 24 hours.

So first I entered the tasks using normal calendar, not doing anything special.



Now the schedule knows that the amount of work for a 2 day tasks I say there is 16 hours correct?

Only then, when I adjust the calendar to a 24 hour calendar, it will reduce the duration to 1 day?

And I saw that there is a readily available 24 hour calendar, but I need a 24 hour AND weekend calendar together so I must create a new one and assign that one to these tasks right?

So is my logic correct when I said I first enter them using normal calendar so project knows that normall it is a 2 day task?

And how do I assign some of the tasks to the calendar - I open the advanced view of EACH of those activities one by one and assign my 7/24 calendar to them?
Reply With Quote
  #2  
Old 05-12-2014, 10:43 AM
JulieS JulieS is offline assign weekend 24 hr calendar to some tasks Windows 7 64bit assign weekend 24 hr calendar to some tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The 24-hours calendar in Project already includes weekends as working time. It is 24 hours per day 7 days per week 365 days per year.

A 16 hour task will still show as 2 days duration because although you have assigned the 24 hours calendar, the definition of "day" = 8 hours. The start and finish date/times will be correct.

Add the Task Calendar field to a task view to quickly set calendars.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
assign weekend 24 hr calendar to some tasks work during weekend outside normal calendar Intruder Project 13 02-27-2014 01:35 PM
assign weekend 24 hr calendar to some tasks Assign resource groups to tasks jjmclell Project 2 12-17-2012 04:28 AM
Calculating Weekend Allowance WinIDS Excel 6 09-02-2011 01:27 AM
Change font size of tasks in pane under Calendar ghumdinger Outlook 2 08-16-2011 06:29 PM
Code to auto-forward weekend messages Whang Outlook 0 06-16-2010 02:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:13 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft