#1
|
|||
|
|||
![]()
If I go into bar styles on the gantt chart area, I can select the drop down that allows me to put resource names against each bar.
However, it always shows the percentage allocation Eg. Design Engineer [80%], Design Manager [20%] Is it possible to get it to show the hours instead? So that it would say: Design Engineer [32h], Design Manager [8h] Percentages mean nothing to me or my colleagues who would be more concerned with budgeted hours than percentage allocations over time. Or are there any other views that might allow me show programme activities, resources against that activity and each resources budgeted hours? Thanks in advance to anyone who can help.... |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Intruder | Project | 7 | 02-02-2014 01:50 PM |
Can two sets of task bars be shown on the Gantt? | steve@stanley | Project | 1 | 07-23-2012 06:03 AM |
Making Gantt chart and resource usage views independently viewable in MSP 2007 | proj12 | Project | 1 | 02-28-2012 06:59 AM |
![]() |
NeoFax | Project | 4 | 06-07-2011 08:32 AM |
gantt bars with text and i'm losing the bar when i print | oompa_l | Project | 0 | 11-17-2010 01:16 PM |