Resources pool showing file name
Hi,
I've created a resources pool file and all the different project files are now going to be using this for their resources. The problem is that when I run reports - eg: resources usage (view or creating a report) - it brings all the tasks by resource - which is great. However, as the tasks are for a bunch of different project, it'd be really good to see the 'project name' or the 'file name'. However, I cannot see how / where to do that? Is it possible at all? Many many thanks! |
#2
|
|||
|
|||
I got it!
Basically, I asked inserted a column in the resource usage view with the 'project'. Great, thank you! |
#3
|
|||
|
|||
Glad you were able to sort it out.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resource pool with Sharepoint | codeghi | Project | 3 | 02-28-2014 11:39 AM |
Outlook Data File subfolder not showing messages | phrankb | Outlook | 0 | 12-24-2013 05:26 AM |
Resource Pool / export | Bec82 | Project | 3 | 08-16-2011 11:11 AM |
Use only rsource pool | gdallas | Project | 0 | 11-25-2010 01:10 PM |
Is there a function on MS Word showing the lastest changes made on a word file? | _____ | Word | 2 | 10-30-2010 05:33 AM |