Journeyman3000 Journeyman3000 is offline Autoscheduling jumps by years in advance Windows 7 64bit Autoscheduling jumps by years in advance Office 2007
Novice
Autoscheduling jumps by years in advance
 
Join Date: Mar 2014
Posts: 1
Journeyman3000 is on a distinguished road
Default Autoscheduling jumps by years in advance

I am very new to MS project. I have a general idea after looking around, but I've run into a problem.



I have created a standard project. I've added some data and have created a resource against the data. The resource is for 1200%, e.g. 12 people.

I went to autolevel, but I get some of the project for a small part of the year, and a bunch of other projects apparently being done years in advance.

This is like totally bogus. This completely screws the project.

Why is this happening and can somebody offer some advice please

Cheers
Reply With Quote
  #2  
Old 03-24-2014, 08:05 AM
JulieS JulieS is offline Autoscheduling jumps by years in advance Windows 7 64bit Autoscheduling jumps by years in advance Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Too broad of a question for me to answer without actually seeing the project. Is it one you can share?
Reply With Quote
  #3  
Old 04-01-2014, 12:15 AM
Avitra Avitra is offline Autoscheduling jumps by years in advance Windows 7 64bit Autoscheduling jumps by years in advance Office 2010 64bit
Novice
 
Join Date: Apr 2014
Location: Zurich
Posts: 1
Avitra is on a distinguished road
Default

I had the same problem and for the life of me can't understand why.

However, without really understanding, the solution is very simple - go to the gantt chart and actually shorten the bars. than - level all.
It worked for me
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Autoscheduling jumps by years in advance Converting serial number to years, months and days hannu Excel 6 02-14-2013 09:21 PM
Comparison jumps to end MarshallAbrams Word 2 03-21-2012 04:04 AM
page jumps when scrolling geoffoto Office 0 07-20-2011 07:14 PM
Picture jumps to the next page Vananil Drawing and Graphics 2 05-31-2010 01:42 AM
Autoscheduling jumps by years in advance Using Field Codes to Calculate 5 years from a Date vandy Word 1 09-23-2009 11:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft