Old 03-29-2014, 04:09 AM
mijam mijam is offline non working day view Windows 7 32bit non working day view Office 2013
Novice
non working day view
 
Join Date: Mar 2014
Posts: 1
mijam is on a distinguished road
Default non working day view

Hiya,

I'm a beginner with Project so please bear with me. what I'm asking may be a simple task, but I'm dammed if I can figure it out even with the power of Google and You Tube.



What I'm after is to display several tasks within one project but with only the relevant working days shown on the chart for the given task.
e.g.
TASK Course 5 DURATION 10 weeks START today END autocomplete
this course only runs on a Tue/Wed so I would like to show only Tue/Wed working days on this row.

TASK Course 6 DURATION 10 weeks START today END autocomplete
this course only runs on a Thur/Fri so I would like to show only Thur/Fri working days on this row.

I've tried but I can only view one calendar at a time. I've created 2 calendars Tue/Wed only and Thur/Fri only with the other days set to non-working days.

any help appreciated
mijam
Reply With Quote
  #2  
Old 03-29-2014, 10:52 AM
JulieS JulieS is offline non working day view Windows 7 64bit non working day view Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can create task calendars (as it sounds like you may have) to restrict the scheduling of the tasks to their respective days. By assigning the task calendars, the task will be scheduled only for those days. To assign the task calendar, show the Task Information (right click) and set the Task Calendar on the advanced tab.

However, the display of non-working time (default gray shade) is set for the entire Gantt chart - you cannot show only Tuesday/Wednesday on Course 5 and Thursday/Friday on Course 6.

I personally would turn off the display of non-working time as your definition is variable.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Contact view filter not working gebobs Outlook 2 03-10-2014 06:28 AM
How can I fix a print view problem that causes it to stop working.. Excel 2007, Vista birdie123 Excel 0 08-18-2012 12:02 PM
non working day view How to save a PPT file in 'Reading View' to be opened always in 'Reading View' ItzVickey PowerPoint 2 08-08-2012 09:23 AM
non working day view Separate projected view vs. PC view possible? frank14612 PowerPoint 3 02-19-2012 02:43 AM
non working day view How do I view a document in "normal" view... JennK13 Word 4 08-15-2011 11:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:08 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft