using a predecessor twice
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default using a predecessor twice

it is not possible to use one task twice, for an activity's predecessor. lets say installation of drywall and taping tasks. I want to link taping as

drywall SS + 3 day

which i do, and it is fine



but

taping also can not finish, before drywall can finish. impossible. so, how to show this? MS project doesnt let me to also put a drywall FF as a predecessor to taping

i do not and can not end up with wrong schedule anyway, as my taping can not be complete before drywall is finsih so my dates are ok but as far as showing the relationships i am asking
Reply With Quote
  #2  
Old 03-07-2014, 07:12 AM
Guloluseus Guloluseus is offline using a predecessor twice Windows 7 64bit using a predecessor twice Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

If you have drywall as a predecessor to taping with an SS constraint, you cannnot have an FF predecessor as well- you would be to link start date to ther start AND finish of the predecessor.

I would suggest that if you know the amount of time between when drywall should be complete and tryingtaping should be complete, you use an FF+ predecessor. If you assume that taping should finish 1 day after walling finishes, the the predecessor for taping would be (drywall) FF+1d. This would link the two and ensure that taping i salways seen as finishing after the walling.
Reply With Quote
  #3  
Old 03-07-2014, 04:52 PM
JulieS JulieS is offline using a predecessor twice Windows 7 64bit using a predecessor twice Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can use milestones and a hammock task. Add a Milestone called begin taping with a SS+3day link to drywall installation. Add another milestone with a FF relationship to drywall.
Then follow the directions at the link below to create taping as a hammock.

http://support.microsoft.com/kb/141733
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
using a predecessor twice Predecessor name displayed in a text field Leah Project 7 02-07-2014 03:26 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM
using a predecessor twice arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
using a predecessor twice New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:35 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft