Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 03-04-2014, 08:08 PM
Mav Mav is offline Project Hours Windows 7 32bit Project Hours Office 2010 32bit
Novice
Project Hours
 
Join Date: Mar 2014
Posts: 7
Mav is on a distinguished road
Default Project Hours


Hello Forum,

I need 1 resource (place) to work 20 hours a day duration and may have more hours assigned than duration. Such as, 32 hours of work but will take 16 hours to complete (2 people) leaving 4 hours remaining in day 1.

Tasks are auto scheduled. I've tried setting calendar to 20 hours working time and tasks to fixed work. I enter 32 hours in the work column and enter 16 hours in the duration column but project doesn't see to spread the hours correctly. It spreads the hours 16 hours over 2 days. Project is spreading the duration longer than the set duration.

How is the best way to set this up?

Thanks in advance
Reply With Quote
  #2  
Old 03-05-2014, 01:19 PM
JulieS JulieS is offline Project Hours Windows 7 64bit Project Hours Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't fully understand what you are seeking. What is the place?

if you intend that two resources will work on the task for eight hours per day (16 hours in total per day) - assign two resources. Or ensure you have 200% of the resource assigned to be able to generate 16 hours of work per day. The duration is two 8 hour days the work is 32 with 16 hours of work per day for 2 days.
Reply With Quote
  #3  
Old 03-05-2014, 06:20 PM
Mav Mav is offline Project Hours Windows 7 32bit Project Hours Office 2010 32bit
Novice
Project Hours
 
Join Date: Mar 2014
Posts: 7
Mav is on a distinguished road
Default

The "place" is an area that I want to capture the hours worked in. Like at a work bench or similar area.

I want this resource to have a 20 hr work day. If I have 2 people working in this resource area for 16 hours (duration) I would set the work at 32 hours (work).

The problem is that when I put 32 hours of work and 16 hours of duration Project spreads the hours (work) longer than the 16 hours (duration). Instead of 32 hours (work) and only one day because 16 hours will fit within one 20 hour day, Project spreads the hours over 2 days.
Reply With Quote
  #4  
Old 03-07-2014, 07:18 AM
Guloluseus Guloluseus is offline Project Hours Windows 7 64bit Project Hours Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Not sure if I understand the problem correctly, let me know if I am wrong.

you have an area that will be in use for 20 hours a day, regardelss of how many people are there, so you effectively want project to work out nmumber of people if you tell it how many hours were worked?

I would suggest that you change the task type from Fixed Work (which I assume it is on) to Fixed Duration. this would enable you to inout the amount of work done, and project would maintain the task as a 1 day duration.

Again sorry if this isnt what you are asking still a tad confused with it.
Reply With Quote
  #5  
Old 03-07-2014, 04:47 PM
JulieS JulieS is offline Project Hours Windows 7 64bit Project Hours Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do your human resources work 20 hours per day or only the space? If your resources' calendars only allow 8 hours per day - the 32 hours will go to the next day - even if the space allows 20 hours of work per day.

What time does the task start?

Please describe the following:
Working time for the room calendar.
Working time for the human resources.
Starting date/time for the task.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Hours Hours in MS Project Changed ayeh Project 14 02-12-2014 10:41 AM
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM
Project Hours How to add hours together PomDave Excel 3 09-05-2011 04:43 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft