Assigning Resources and percent complete
Hello, I need help please! Ok I have 2 task that I am assigning 1 resource to. Task 1 is 80% of the resource and Task 2 is 20% of the resource. Ok here is my issue....for an example Task 1 is 100% complete and Task 2 is 0%. So when I go to my resource page and look at %work complete it will say 50%. I guess it says 50% because 1 out of 2 task are complete. But in reality it should say 80% complete because Task 1 is 80% of the resource and it is complete. Is there a way to have it calculate the actual percent of the resource that is complete?? Let me know if you need additional information.
|
#2
|
|||
|
|||
Try looking at Percent Work complete - not percent complete. The percent work complete should show you more accurate data.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Assigning finish date to work with %complete | Guloluseus | Project | 3 | 12-12-2013 10:16 AM |
Assigning Resources to Tasks | rickw262 | Project | 1 | 01-18-2013 04:46 AM |
Assigning calendars to resources automatically | david_23 | Project | 3 | 03-30-2012 07:43 AM |
Percent Complete doesn't change End Date?? | jrwpmw | Project | 2 | 03-11-2010 01:40 PM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |