Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #14  
Old 02-27-2014, 01:35 PM
JulieS JulieS is offline work during weekend outside normal calendar Windows 7 64bit work during weekend outside normal calendar Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The first question would be why is the series of tasks moving? If the predecessor has been delayed - delay the predecessor and yes, you may have to add a constraint.

If the series of tasks is delayed because the predecessor is taking longer - increase the remaining duration when tracking to show the increase in duration and work.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
showing calendar days by keeping normal workday calendar ketanco Project 11 11-01-2013 08:27 AM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
Calculating Weekend Allowance WinIDS Excel 6 09-02-2011 01:27 AM
Change Calendar to 4 day work week J C M Outlook 1 04-28-2011 02:20 PM
Code to auto-forward weekend messages Whang Outlook 0 06-16-2010 02:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft