correct way to enter tasks
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default correct way to enter tasks


which one is correct way to enter tasks?

1-entering a tasks duration, even if you know the total amount (say sf) of the task and how many people you will assign to it,

or

2-just entering the square feet of quantity, and the units (labor) that will perform the task, and let project calculate the duration.


lets say I have 500 sf of wall to paint. I know this for a fact. I have 2 painters who can do 100 sf everyday. I know this for a fact too.

based on this, do i build my schedule like in 1 or 2? which is correct way?

also is there a way to enter 400sf for the total quantity of work? can work be sf i mean?
Reply With Quote
  #2  
Old 02-10-2014, 01:05 PM
JulieS JulieS is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Either method is fine. It all depends on which value (duration or work) you are the most confident in. I personally find that people are usually more accurate regarding work than duration, so I am inclined to enter the task, enter the work upon resource assignment and let Project calculate duration.
Reply With Quote
  #3  
Old 02-10-2014, 01:24 PM
ketanco ketanco is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2007
Expert
correct way to enter tasks
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

so i will not (and can not) tell MS project that labor is doing 100sf/day, or I have 500 sf of wall, and there is no way to tell this right? i mean i can not enter sf quantities there correct?

all i can do is, i tell ms project either a 2.5 day duration, and assign 2 full time labor as in 1

OR

i tell ms project that i have a total of 40 hours of work, and i assigned 2 labor to it, after which it calculates 2.5 day

am i correct?
Reply With Quote
  #4  
Old 02-10-2014, 01:34 PM
JulieS JulieS is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Sorry, no. Project does not understand concepts of X amount of square footage per day. I understands Work, Duration, and Assignment units. By you telling Project Work, it will calculate Duration based upon the Work and the resource assignment units. 1 resource working 8 hours per day can accomplish 40 hours of work in 5 days. 1 resource working 6 hours per day can accomplish 40 hours of work in 6.67 days.
Reply With Quote
  #5  
Old 02-10-2014, 02:04 PM
ketanco ketanco is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2007
Expert
correct way to enter tasks
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

ok and, work is always entered in hours right?

we do not and can not enter sf or sf / day etc correct?

so in other words, i enter 40 hours because i calculate it outside of ms project myself... correct?
Reply With Quote
  #6  
Old 02-10-2014, 02:40 PM
JulieS JulieS is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Work may be entered in minutes, hours, days, weeks, or months. Work cannot be entered in square feet or square feet/day. You can enter variable consumption (sf/day) for material resources - not work.
Reply With Quote
  #7  
Old 02-11-2014, 05:14 AM
ketanco ketanco is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2007
Expert
correct way to enter tasks
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

ok so i enter 40 hours because i calculate it myself outside ms project correct?
Reply With Quote
  #8  
Old 02-11-2014, 07:42 AM
JulieS JulieS is offline correct way to enter tasks Windows 7 64bit correct way to enter tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes. Project cannot perform calculations based upon square footage.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
Which .pst is the correct .pst dbsoccer Outlook 1 04-08-2012 12:12 PM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
correct way to enter tasks Enter + Alt + Enter is not working inside the text box! why???? Jamal NUMAN Word 3 04-17-2011 05:35 PM
So what is the correct value of PONT_STRING anyway? DrDOS Outlook 0 11-21-2010 04:30 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:36 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft