Calculating 6.5hr work days
 
Join Date: Feb 2014
Posts: 3
altja is on a distinguished road
Default Calculating 6.5hr work days

Ok that title sucks.

Here is what I am trying to do. I have developers that work 8 an hour day, but they don't code for 8 hours in a day. So I am trying to get the timeline to represent a 6.5 hr day. I go into project options and set hours per day at 6.5 and hours per week as 32.5. However, if I put in a task of 8 hours in it still claims that the developer is finishing the task in one day. The expected result would be that they would finish it the next day.



How should I be doing this?

I want to avoid setting the developer at (6.5/8) 81.25% because then i have to adjust that everyplace.
Reply With Quote
  #2  
Old 02-10-2014, 01:02 PM
JulieS JulieS is offline Calculating 6.5hr work days Windows 7 64bit Calculating 6.5hr work days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you don't want to change the Resource's max units - then you'll need to change the developers calendars to only allow them to work 6.5 hours per day. If you then assign the resource 8 hours of work, the task finish date will change.
Changing this in Project Options is not the answer.
Reply With Quote
  #3  
Old 02-10-2014, 02:54 PM
altja altja is offline Windows 8 Office 2013
Novice
Calculating 6.5hr work days
 
Join Date: Feb 2014
Posts: 3
altja is on a distinguished road
Thumbs up Thanks that worked for me.

Thanks that worked for me.
Reply With Quote
  #4  
Old 02-10-2014, 03:11 PM
JulieS JulieS is offline Calculating 6.5hr work days Windows 7 64bit Calculating 6.5hr work days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Glad to know changing the resource's calendar got you what you needed. Thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) John Franklin Project 22 11-12-2013 03:19 PM
Calculating 6.5hr work days 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Calculating 6.5hr work days 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
Calculating 6.5hr work days Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:12 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft