Yes. it requires a custom report - but pretty easy to do:
Project Ribbon > Reports, Custom New. Select Resource. On the Resource Report definition page - rename the report. Select any time range you need. I would likely apply the Work Resource Filter. Click the details tab and select Cost Rates. Click OK You should now have the report showing each resource along with each of the 5 cost rates tables plus any changes. |
|
![]() |
||||