  #1  
Old 02-06-2014, 09:44 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 8 Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default Hours in MS Project Changed

Not sure why hours assigned to resources changed. For example, we had 30 hours for one employee under work and baseline but when we ran a baseline cost report, her hours were almost doubled (58) under baseline work but her hours under cumulative work was correct. Can anyone tell me why and how to fix that?
Reply With Quote
  #2  
Old 02-07-2014, 05:19 AM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What version of Project? If you are using Project 2010 you should be at SP-2. The baseline data is not changed by Project - is it possible that someone either manually changed the baseline or saved a new one? You mention the Baseline Cost Report - does the data appear correctly if you add the Baseline Work to a view, instead of running the report?
Reply With Quote
  #3  
Old 02-07-2014, 07:53 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

Thanks for your reply. We are using Project 2010 and we have saved a new one. And when we add the baseline work in a view, it is correct. So why is it different from the report we run?
Reply With Quote
  #4  
Old 02-07-2014, 08:31 AM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You said you are running the Baseline Cost report - what level of detail are you viewing? Without seeing your report parameters and your project it is impossible to guess why you are seeing incorrect data. As a first step make sure you are up to date on service packs and cumulative updates.
Reply With Quote
  #5  
Old 02-07-2014, 09:00 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

We first saw the variance at first level, then we looked at each subtask and found out only 1 subtask has this issue. All others are correct.
Reply With Quote
  #6  
Old 02-07-2014, 03:27 PM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If it has only changed on one task - my bet is someone changed the field manually.
Reply With Quote
  #7  
Old 02-10-2014, 09:32 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

Julie, what's really frustrating is that we deleted that task and added a new one and it's still giving us the same problem. When we view the resource assignment in Project, it gives us the right number of baseline hours but when we run a report, they just went up.
Reply With Quote
  #8  
Old 02-10-2014, 09:50 AM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do you have SP-2 installed to Project 2010? When you added the new task, did you re-baseline it? Are you looking at the baseline cost for the summary task or the detail task?

Do you have resources assigned to the summary task?
Reply With Quote
  #9  
Old 02-10-2014, 10:41 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

We don't have SP-2. We did re-baseline it after deleting that task and adding a new one loaded with the same resources. No resources were assigned to the summary task but when I noticed the difference at the summary level and drilled down, that's when we discovered one specific task with this issue.
Reply With Quote
  #10  
Old 02-10-2014, 11:07 AM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Please install SP-2 at a minimum and consider installing the December 2013 Cumulative update after installing SP-2.
Reply With Quote
  #11  
Old 02-10-2014, 11:38 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

Let me try that and see if that takes care of the problem. Thanks!
Reply With Quote
  #12  
Old 02-10-2014, 12:01 PM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

After having SP2 installed, I can't run any visual reports now. I keep getting an error message saying "an unknown error has occurred and the requested action could not be completed at this time".
Reply With Quote
  #13  
Old 02-10-2014, 01:03 PM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Have you restarted you machine after the installation of SP-2?
Reply With Quote
  #14  
Old 02-12-2014, 08:34 AM
ayeh ayeh is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2010 64bit
Novice
Hours in MS Project Changed
 
Join Date: Feb 2014
Location: DC
Posts: 8
ayeh is on a distinguished road
Default

Julie, thanks so much. I think SP2 did solve the problem! We can't run reports to see costs by week but we can still run "by month" reports and the numbers tie!! Thanks so much!!
Reply With Quote
  #15  
Old 02-12-2014, 10:41 AM
JulieS JulieS is offline Hours in MS Project Changed Windows 7 64bit Hours in MS Project Changed Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thank you for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM
Hours in MS Project Changed How to add hours together PomDave Excel 3 09-05-2011 04:43 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:11 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft