kuwanderer kuwanderer is offline Best way to set up big project Windows 7 32bit Best way to set up big project Office 2010 32bit
Novice
Best way to set up big project
 
Join Date: Jan 2014
Posts: 1
kuwanderer is on a distinguished road
Default Best way to set up big project

Hey,


I've been working on creating a huge project. It basically is a timeline of the life of a shipping container that goes through 50+ different events divided into a design, 1st production, and Build phases. I've got it build and it works great in project. My problem is organizing it with 150+ containers going through the timeline during the projects life. My container will be built in waves with 5-10 starting the timeline together then another wave the following week.

The best solution I've found is making each event a summary task that contains each container in the program. So there will be around 50 summary task(event tracking points) containing 150+ containers. I am using different text columns for Project manager, Container ID, and Category so I can filter to see just the container in the timeline that I want. It works. But When I filter to show just the container for 1 project manager the % compete doesn't reflect what is filtered. It reflects everything.

So, Is there a better way to organize the project? Is there a way to have % complete for each summary task reflect only what is filtered? I'll try an attach a pic to show what I am doing.


Thanks for any help
Reply With Quote
  #2  
Old 01-28-2014, 03:02 PM
JulieS JulieS is offline Best way to set up big project Windows 7 64bit Best way to set up big project Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Its a bit tough for my old eyes to see your Gantt chart view. I'm guessing you have items for each of the containers organized by summary task?

If you have coded each task with the container ID consider creating a custom group (by container ID) to see summary level % complete. Filtering does not recalculate the % complete only for visible tasks.

Post back if you need more guidance on setting up the group.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Example for using Ms Project safaa Project 1 11-13-2012 05:30 PM
Example for using Ms Project in construction project safaa Project 1 11-08-2012 05:54 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:52 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft