SomewhereinTX SomewhereinTX is offline Firm constraints wouldn't keep the date fixed? Windows 7 64bit Firm constraints wouldn't keep the date fixed? Office 2010 64bit
Novice
Firm constraints wouldn't keep the date fixed?
 
Join Date: Dec 2013
Posts: 11
SomewhereinTX is on a distinguished road
Default Firm constraints wouldn't keep the date fixed?

Hello All,



Same project, same schedule in MSP that I was inquiring about before... To recall, this is a schedule that's been updated by our local team in another country and is sent to me weekly to produce progress reports.

First 25 lines or so are all milestones acting as a de facto high level summary of the schedule. It was created mainly for the management so when they look at it, they can easily take it all in, without going through other 300+ lines.

Against my ongoing pleas, the local project team puts constraints (Start No Earlier Than) on all the milestone tasks, both in the "summary" and the rest of the schedule. The summary tasks and the corresponding schedule tasks are connected via predecessor/successor relationships.

Interestingly enough, I noticed that last time when I got the updated file from them, updated the project status date (for whatever reasons the local team can't get this function to work so I do it form here), and hit Update Project (Re-schedule uncompleted work after ../..), MSP re-calculated future start-finish dates for the milestones correctly (in my opinion! ) by pushing them out (as the project is delayed). Which means the constraints (SNET) didn't work! I was just wondering why this could happen...as the whole point of firm constraints is to keep the date fixed.

Many thanks.
Reply With Quote
  #2  
Old 01-22-2014, 05:27 PM
JulieS JulieS is offline Firm constraints wouldn't keep the date fixed? Windows 7 64bit Firm constraints wouldn't keep the date fixed? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The Reschedule incomplete applies its own SNET constraints. Remember SNET constraints means the task can start later - just not any earlier.
Reply With Quote
  #3  
Old 01-23-2014, 12:31 PM
SomewhereinTX SomewhereinTX is offline Firm constraints wouldn't keep the date fixed? Windows 7 64bit Firm constraints wouldn't keep the date fixed? Office 2010 64bit
Novice
Firm constraints wouldn't keep the date fixed?
 
Join Date: Dec 2013
Posts: 11
SomewhereinTX is on a distinguished road
Default

Duuuh... I knew I'd feel...well, like not the smartest tool in the shed. Thanks Julie, appreciate it!
Reply With Quote
  #4  
Old 01-23-2014, 01:46 PM
JulieS JulieS is offline Firm constraints wouldn't keep the date fixed? Windows 7 64bit Firm constraints wouldn't keep the date fixed? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome, Anna
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Firm constraints wouldn't keep the date fixed? Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
How to add a fixed value to an entire column? mikehende Excel 11 12-12-2012 02:47 PM
Firm constraints wouldn't keep the date fixed? How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Constraints in MS Project Antares Project 11 12-09-2011 10:55 AM
Firm constraints wouldn't keep the date fixed? Time now--fixed? markg2 Excel 1 09-19-2010 12:05 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:06 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft