SomewhereinTX SomewhereinTX is offline Changing Actual Finish dates changes original Finish dates Windows 7 64bit Changing Actual Finish dates changes original Finish dates Office 2010 64bit
Novice
Changing Actual Finish dates changes original Finish dates
 
Join Date: Dec 2013
Posts: 11
SomewhereinTX is on a distinguished road
Default Changing Actual Finish dates changes original Finish dates

Hi,



First time in this community and an unexperienced user of MS Project, so would appreciate any help.

There is a pretty extensive schedule in MSP originally created by someone else which is maintained by a different "someone else", and this "different someone else" sends me the freshly updated schedule weekly so that I can run a few reports on the project progress (or a lack of thereof).

This "different someone else" is not exactly a super user of MSP either, so today he surprised me with this question: When I tried to update the “Actual Finish”, the “Finish” column changed to the same date. What could be wrong?
They updated the project weekly multiple times before but never mentioned this problem, hence I assume this is new. So what could be wrong this time and why adjusting actuals made original dates change accordingly?

Apologies for what probably is a very naive question and many thanks

P.S. In case if anyone thinks this has something to do with baselines - and fyi - we have baseline start and finish columns in this schedule, and these are "locked", meaning we don't change them unless with the mngt's permission. The last baseline (so far there's a total of three) was set back in Sep 2013.
Reply With Quote
  #2  
Old 12-20-2013, 04:52 AM
JulieS JulieS is offline Changing Actual Finish dates changes original Finish dates Windows 7 64bit Changing Actual Finish dates changes original Finish dates Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There isn't anything wrong going on. The Finish date of a task will change to match an Actual Finish. The comparison for variance is between the Baseline Finish and either the Actual Finish (if the task is complete) or the Finish if the task is incomplete.

It is as expected and didn't just start happening - the user may have just noticed it.

I hope this helps.
Reply With Quote
  #3  
Old 12-20-2013, 07:14 AM
SomewhereinTX SomewhereinTX is offline Changing Actual Finish dates changes original Finish dates Windows 7 64bit Changing Actual Finish dates changes original Finish dates Office 2010 64bit
Novice
Changing Actual Finish dates changes original Finish dates
 
Join Date: Dec 2013
Posts: 11
SomewhereinTX is on a distinguished road
Default

Thank you Julie, it does. As the goal is to see how we are doing on the task progress, I think I will re-introduce the Baseline 3 Start and Baseline 3 Finish columns into the schedule; maybe both but Baseline 3 Finish for sure (I took them out earlier as the schedule was getting to be to big to take all the columns in at once), and will also create a Finish Variance column, so that we can track "Finish minus Baseline 3 Finish". Do you think this will do the trick or would there be anything else that I didn't think of?
Thanks so much again.
Reply With Quote
  #4  
Old 12-20-2013, 10:25 AM
JulieS JulieS is offline Changing Actual Finish dates changes original Finish dates Windows 7 64bit Changing Actual Finish dates changes original Finish dates Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can have Project calculate variance off any single baseline by changing the Earned Value option in File > Options, Advanced.

Sadly, you cannot show multiple variance calculations at once, but a ProjDateDiff function in one of the spare Duration fields can allow you to calculate and show variances against several baselines.

You're most welcome
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing Actual Finish dates changes original Finish dates Calendar without actual dates parnol01 Project 1 12-16-2015 09:30 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Changing Actual Finish dates changes original Finish dates duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Changing Actual Finish dates changes original Finish dates displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft