Manual Task End Date
Is there an option to select where an end date of a manual task does not impact the end date of the overall auto project "header" task (row 1)?
Thank you |
#2
|
|||
|
|||
I'm guessing you'd like a task end date to end after the Project Summary task? No, sorry. The finish date of the Project Summary task (should be row zero, not one) will be the latest date of all tasks (auto or manually scheduled) in the project.
|
|