Morning



I have a programme for a large engineering project, where many tasks have been started but have not been completed. this often occurs when we only have access to part of a section, and so achieve say) 50% with the remainder to be carried out at a later date.

Is it possible for a split task to have a resume date set, or is it tied to the current update date? the only other way I can see to get around this is to create a duplicate set of activities called "part 2" or somesuch, and mark these off separately.

The reason for attempting this is that there is a monthly KPI checklist, and we lose points where activities are marked as beig under way in the programme, but are not actually taking place.

Prog is in MSP2010, but will also be converted to MSP 2007 for others to view, so a 2010 soluton would be great, if it works in 2007 as well even better.

Thanks
Reply With Quote
  #2  
Old 12-09-2013, 10:22 AM
JulieS JulieS is offline Assigning finish date to work with %complete Windows 7 64bit Assigning finish date to work with %complete Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You may select individual tasks and use the Update Project - reschedule uncompleted work command (Project ribbon 2010 or Tools Tracking Updating Project in 2007) to split the task and move the remaining work to a new date.
Reply With Quote
  #3  
Old 12-12-2013, 04:49 AM
Guloluseus Guloluseus is offline Assigning finish date to work with %complete Windows 7 64bit Assigning finish date to work with %complete Office 2010 32bit
Competent Performer
Assigning finish date to work with %complete
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Thanks for the reply

That is generally how I update the programme, with the "start after" date being the update date- so if the update is done on 4 june 2015, all activities started but not completed will recommence on 4 june 2015. The problem is that if I set the recommence date to a months time, ALL activities would recommence then.

Had I thought about it more, I wold have realised that want I wanted was for Project to reschedule tasks based on what I knew would happen, as opposed to what the progrmme showed. I will go with the individual rescheduling as you suggest, and hope that the number of tasks drops

Thanks J, marking this one closed.
Reply With Quote
  #4  
Old 12-12-2013, 10:16 AM
JulieS JulieS is offline Assigning finish date to work with %complete Windows 7 64bit Assigning finish date to work with %complete Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. Sadly, Microsoft has not yet developed the "this is what I knew would happen" add-in for Project - so I'm afraid it's up to you.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Assigning finish date to work with %complete how to calculate backwards from a set finish date ketanco Project 1 02-07-2013 06:50 AM
Assigning finish date to work with %complete Units not properly updated after a Finish Date Change zi1 Project 1 08-04-2012 05:55 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
Assigning finish date to work with %complete In Outlook 2003 auto complete won't work Meenie Outlook 2 06-11-2009 08:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:49 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft