Well, in response to your last suggestion, the latter one with de-selecting the round off to whole days did not work.
But... it seems that the former one, the 24 default calendar coupled with all the other settings and a 12 hour work day seems to. Hooray for that. I am in the middle of something just at the moment. I will play around with it tonight, and compose a new schedule and insure that it is as it seems. I will let you know if it does, and the reply will be there when you come in tomorrow. Thank you, very much. |
#2
|
|||
|
|||
![]()
You're welcome John. Let us know how you get along.
|
#3
|
|||
|
|||
![]()
ugh! I could not do it again tonight.
>24hr calender >Tools>Change working time>Options>12hr/day>84hr/wk What did I miss? |
#4
|
|||
|
|||
![]()
I'm not sure what is going on.
24 hours calendar set as the project calendar in Project Information. Day defined as 12 hours Week as 84 Default start time 7:00 am Default end 7:00 pm? |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
John Franklin | Project | 3 | 10-30-2013 08:16 AM |
![]() |
hanvyj | Project | 9 | 07-09-2013 07:27 AM |
Can Excel Deduct 30 Minutes from an 8 1/2 Hour Cell? | tatihulot | Excel | 4 | 05-16-2013 04:30 PM |
Calendar work days in advance | paol:o | Outlook | 4 | 05-27-2012 07:23 PM |
![]() |
maruchi | Project | 1 | 06-17-2010 08:06 AM |