Old 11-11-2013, 03:08 PM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Red face


You're welcome John. Let us know how you get along.
Reply With Quote
  #17  
Old 11-11-2013, 06:49 PM
John Franklin John Franklin is offline 12 hour work days (shifts) Windows XP 12 hour work days (shifts) Office 2001 for Mac
Novice
12 hour work days (shifts)
 
Join Date: Oct 2013
Posts: 19
John Franklin is on a distinguished road
Default

ugh! I could not do it again tonight.

>24hr calender
>Tools>Change working time>Options>12hr/day>84hr/wk

What did I miss?
Reply With Quote
  #18  
Old 11-12-2013, 08:04 AM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure what is going on.

24 hours calendar set as the project calendar in Project Information.
Day defined as 12 hours
Week as 84
Default start time 7:00 am
Default end 7:00 pm?
Reply With Quote
  #19  
Old 11-12-2013, 12:25 PM
John Franklin John Franklin is offline 12 hour work days (shifts) Windows XP 12 hour work days (shifts) Office 2001 for Mac
Novice
12 hour work days (shifts)
 
Join Date: Oct 2013
Posts: 19
John Franklin is on a distinguished road
Default

All of that is correct.
Specficly were should I chech and insure the 12 hour day.
Yes, work day/shift is 7 am to 7pm. Should I tell it somewhere to tell it 7pm to 7am for the night shift?
Thanks
Reply With Quote
  #20  
Old 11-12-2013, 02:51 PM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The setting is in Tools > Options. There is only one setting per project. After you create the links between your tasks, it will schedule them as needed. The default begin and end is just for tasks scheduled without predecessors and successors.

So, what is not working now?
Reply With Quote
  #21  
Old 11-12-2013, 02:59 PM
John Franklin John Franklin is offline 12 hour work days (shifts) Windows XP 12 hour work days (shifts) Office 2001 for Mac
Novice
12 hour work days (shifts)
 
Join Date: Oct 2013
Posts: 19
John Franklin is on a distinguished road
Default

When I put in 6 the activity bar does not go to 6 shifts.
It did yesterday, and I wrote done my steps, but I must have missed something,because I can't get to do it again.


There is a simple setting that I am not seeing. I will work on it tonight some more.

Thanks
Reply With Quote
  #22  
Old 11-12-2013, 03:03 PM
John Franklin John Franklin is offline 12 hour work days (shifts) Windows XP 12 hour work days (shifts) Office 2001 for Mac
Novice
12 hour work days (shifts)
 
Join Date: Oct 2013
Posts: 19
John Franklin is on a distinguished road
Default

Oops, did not answer your question.

When I enter a number representing shifts, it does not give me an accurate task bar.

3d should give me shifts or a day and half or 36 hours
Reply With Quote
  #23  
Old 11-12-2013, 03:19 PM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't know what is going on. If the calendar is set to the 24Hours calendar in Project > Project Information that allows 24 hours per day in working time. If your definition of day is 12 hours, and you enter 3 days - you should see the task starting at 7:00 am and Finishing at 7:00 pm the next day. Is the date/time correct?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) Calendars, 12 hr shifts, 24 hrs/ 7 days John Franklin Project 3 10-30-2013 08:16 AM
12 hour work days (shifts) 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Can Excel Deduct 30 Minutes from an 8 1/2 Hour Cell? tatihulot Excel 4 05-16-2013 04:30 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
12 hour work days (shifts) Half hour added between tasks maruchi Project 1 06-17-2010 08:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft